Statutorily Mandated Reviews of Central Artery/Tunnel Project Building Construction Contracts 1997-199
written by Robert Cerasoli, Massachusetts Office of the Inspector General (Boston, MA: Massachusetts Office of the Inspector General, 1999, originally published 1999), 105 page(s)
Details
- Abstract / Summary
- This document from the Massachusetts Inspector General provides an overview of the contracts granted for the construction of the Central Artery/Tunnel Project (also known as the "Big Dig") in Boston.
- Field of Interest
- Global Issues
- Author
- Robert Cerasoli
- Copyright Message
- Copyright © 1999 by the Massachusetts Office of the Inspector General
- Corporate Author
- Massachusetts Office of the Inspector General
- Content Type
- Accident report
- Duration
- 0 sec
- Format
- Text
- Original Publication Date
- 1999
- Page Count
- 105
- Publication Year
- 1999
- Publisher
- Massachusetts Office of the Inspector General
- Place Published / Released
- Boston, MA
- Subject
- Global Issues, Engineering, Social Sciences, Science & Engineering, Civil and Environmental Engineering, Tunnels, Transportation engineering, Construction, Civil engineering, Engineering, Ingeniería Civil y Ambiental, Engenharia Civil e Ambiental, Tunnel, Construction, Big Dig, Boston, MA
- Keywords and Translated Subjects
- Ingeniería Civil y Ambiental, Engenharia Civil e Ambiental, Tunnel, Construction, Big Dig